EvaluateGuides by Industry7 min readUpdated

Key takeaways

  • DOE and LBNL estimate data centers used about 4.4% of U.S. electricity in 2023, with 6.7% to 12% projected by 2028.
  • Uptime Institute's 2025 survey found a weighted average PUE of 1.54, little changed for six years.
  • In an existing facility, cooling overhead is the part of the bill operators control without touching IT load.
  • Any cooling change must pass change control, starting on redundant (N+1) units with trend data.

For a data center owner or operator, cooling is overhead: energy spent removing heat rather than doing computing. That overhead shows up in the power bill, in how much IT load the facility can sell or support, and in sustainability reports. This page takes the business and operations view. For how CRAC units, CRAH units, chillers and economizers work, see our equipment guide to data center cooling.

The scale of data center energy use

Lawrence Berkeley National Laboratory's 2024 report to Congress, released by the U.S. Department of Energy, estimates that data centers consumed about 4.4% of total U.S. electricity in 2023, or 176 TWh, up from 58 TWh in 2014. It projects 325 to 580 TWh by 2028, or roughly 6.7% to 12% of U.S. electricity (DOE; LBNL). Much of that growth is new construction for AI workloads. The thousands of existing enterprise, colocation and edge facilities, many built a decade or more ago, are also under pressure: utilities are short of capacity, and every kilowatt saved on cooling is a kilowatt available for IT.

PUE: the metric and why it has stalled

Power usage effectiveness (PUE) is total facility energy divided by IT equipment energy. A PUE of 1.5 means that for every kWh delivered to servers, another 0.5 kWh goes to cooling, power conversion losses, lighting and other support loads. Uptime Institute's 2025 global survey found a weighted average annual PUE of 1.54, the sixth consecutive year the figure has barely moved, after falling from 2.5 in 2007 to 1.65 in 2014 (Uptime Institute). Uptime attributes the plateau partly to legacy infrastructure and region-specific barriers to efficient cooling.

PUE also hides a lot. Enterprise server rooms and edge sites, often cooled by a few DX units or a building's general HVAC, frequently don't measure PUE at all. They still pay for cooling overhead; it is just buried in the building's bill. If you run rooms like these, the same approach applies at a smaller scale: meter the cooling units, know what they cost to run, and treat cooling as a controllable expense rather than a fixed one.

For an existing site, that plateau is the opportunity. New builds get the newest designs; older sites carry chillers, DX (direct-expansion) computer room air conditioners and condensing units that have been running for years.

What cooling overhead costs: a worked example

These are illustrative assumptions, not a measured result:

  • Average IT load: 1 MW, running 8,760 hours a year = 8,760 MWh of IT energy
  • PUE 1.54 means total facility energy is about 13,490 MWh, with about 4,730 MWh of overhead
  • Electricity price: the U.S. average industrial price was 9.77 cents per kWh in July 2026, and commercial was 14.53 cents (EIA). Your contract rate will differ.
  • Each 0.05 reduction in PUE saves about 438 MWh a year, worth roughly $43,000 to $64,000 at those prices, plus any demand-charge reduction

The same 438 MWh, viewed as capacity, is about 50 kW of average load that can be reassigned to IT inside an existing utility service. In a capacity-constrained market, that can be worth more than the energy savings.

Constraints that make data centers different

  • Uptime is the product. Service-level agreements, customer audits and reputation outweigh any energy saving. Operators will not accept a measure that adds unmanaged risk to cooling.
  • Change control. Work on critical infrastructure normally needs a method of procedure (MOP), a rollback plan and a scheduled window, even for non-intrusive work.
  • Redundancy. Cooling is usually designed N+1 or 2N, so one unit can be taken out of service or tested while others carry the load.
  • Who pays. In colocation, power costs may be passed through to tenants, so efficiency improvements can sharpen price competitiveness rather than directly cut the operator's bill.
  • Thermal guidelines. Server inlet temperatures must stay inside the range set by ASHRAE and the hardware warranty.

Where cooling efficiency is lost in existing facilities

Overcooling

ENERGY STAR notes that ASHRAE's recommended server inlet range widened from 68–77°F to 64.4–80.6°F, and that data centers can save 4% to 5% in energy costs for every 1°F increase in server inlet temperature. It also warns that higher inlet temperatures can make server fans speed up, offsetting part of the gain, so changes should be tested (ENERGY STAR).

Airflow management

Mixing hot and cold air forces lower supply temperatures and more fan energy. Blanking panels, sealed cable cutouts, and hot-aisle or cold-aisle containment are usually the cheapest wins.

Degraded refrigeration-side performance

Chillers and DX units lose capacity and efficiency over the years. Fouled condenser coils raise head pressure. Inside the refrigerant circuit, compressor oil can coat evaporator and condenser tube walls and insulate them, so the compressor works harder for the same heat removal. Our page on oil fouling explains the mechanism, and how approach temperatures and pressures help separate it from other causes.

Controls drift

Units fighting each other (one humidifying while another dehumidifies), fixed-speed fans, and economizer modes that rarely engage all add overhead that goes unnoticed in a single PUE number.

A measure-by-measure view for operators

MeasureRisk to uptimeNotes
Blanking panels, containment, cable cutout sealsVery lowUsually the first step
Raise supply and inlet setpoints within ASHRAE rangeLow if stagedWatch server fan power and hot spots
Variable-speed fans on CRAC/CRAH unitsLow to mediumRetrofit kits or replacement
Condenser and coil cleaningLowSchedule unit by unit
Economizer optimizationMediumClimate-dependent
Refrigerant-side heat-transfer treatmentLow if done unit by unit on redundant equipmentApplies to refrigerant circuits only
Chiller or CRAC replacementHigher; requires capital and transition planningSee repair, retrofit or replace

How a no-downtime treatment fits

CRYOGENX4 is a one-time treatment injected into operating refrigerant circuits. CryogenX4 says its polarized molecules lift oil film from internal heat-exchanger surfaces and return it to the compressor sump, condition the metal for better heat transfer and improve the lubricity of the existing oil, reducing friction and compressor heat. The company states installation happens while the system runs, with no downtime and no system modifications, by trained, certified technicians, and that most installs take one day.

Two points matter to a data center operator. First, the treatment addresses the refrigerant side: compressors, evaporators and condensers in chillers, DX CRAC units and condensing units. It does nothing for chilled-water or glycol loops, cooling towers, air-side economizers or airflow problems, which need their own measures. Second, the "no downtime" statement still needs to pass your change-control process. A sensible MOP treats one redundant unit at a time while the rest of the plant carries the load.

CryogenX4 reports energy savings of up to 30% and a typical treatment payback of 12 to 36 months; results vary by equipment condition. It states that Intertek certified compatibility with all refrigerants and refrigerant oils. Read our page on OEM warranties and additives before treating equipment under a service contract.

Making the internal business case

Cooling efficiency projects in data centers are rarely approved on energy savings alone. The case usually rests on four arguments, and it helps to quantify each separately:

  • Energy cost. Overhead kWh multiplied by your blended rate, as in the example above.
  • Capacity. Cooling and electrical capacity freed for IT within existing utility service, which matters most where new service takes years to obtain.
  • Equipment headroom. Units that run with lower compressor load have more margin on the hottest days, which supports the redundancy design.
  • Reporting. Lower electricity use reduces Scope 2 emissions reported by the operator or passed to colocation tenants.

Finance teams will also ask whether the spend is operating or capital expense and how payback is calculated. Keep claims conservative and tie every figure to measured data from your own units. A pilot is the cheapest way to replace assumptions with evidence.

How to pilot and verify

  1. Select redundant units serving a stable load, ideally two or three identical CRAC units or one chiller in a multi-chiller plant.
  2. Trend the baseline from your BMS or DCIM system: compressor kW, suction and discharge pressure, supply and return air or water temperatures, and IT load in the zone. Two to four weeks of interval data is a practical minimum.
  3. Calculate kW per ton (or efficiency per unit of heat removed) rather than relying on facility PUE, which moves with IT load and weather. Our guide to kW/ton, EER and COP explains the metrics.
  4. Treat under an approved MOP, one unit at a time, and keep alarm thresholds unchanged.
  5. Compare normalized results using an IPMVP approach (see IPMVP options explained), then decide whether to extend to the rest of the plant.

The what a CryogenX4 pilot measures page lists the data points in detail. For general commercial settings, see commercial HVAC solutions.

Next step: Identify the redundant DX units or chiller you could test without affecting your redundancy rating, and export a month of kW and temperature trends for them. That data set is the starting point for a fair pilot.

Frequently asked questions

Will a lower PUE show up immediately after a cooling improvement?

Not reliably. PUE moves with IT load and outdoor conditions. Measure the treated units directly (kW per ton or kW per kW of heat removed) and normalize for load and weather.

Does a refrigerant-side treatment help liquid-cooled racks?

Only where a refrigerant circuit is involved, such as the chiller that ultimately rejects the heat. Coolant distribution loops and cold plates are water or glycol systems and are outside the scope of a refrigerant treatment.

How do colocation providers benefit if tenants pay for power?

Lower cooling overhead can make pricing more competitive, free capacity within a fixed utility service, and support tenant sustainability reporting.

Is this a substitute for containment and setpoint changes?

No. Airflow and setpoint measures address different losses and are usually cheaper. A refrigerant-side treatment complements them.

Sources

  1. DOE Releases New Report Evaluating Increase in Electricity Demand from Data Centers — U.S. Department of Energy
  2. 2024 United States Data Center Energy Usage Report — Lawrence Berkeley National Laboratory
  3. Uptime Institute Global Data Center Survey 2025 — Uptime Institute
  4. Raise the Temperature (5 Simple Ways to Avoid Energy Waste in Your Data Center) — ENERGY STAR (U.S. EPA)
  5. Electric Power Monthly, Table 5.6.A: Average Price of Electricity to Ultimate Customers by End-Use Sector — U.S. Energy Information Administration

Keep reading

See what your equipment could save

CryogenX4 is a one-time treatment installed while your system runs. Start with a pilot on a few units, measured against a baseline, before you commit to a building or a portfolio.